# List of Schedules

### List of Schedules

After opening a project, use **List of Schedules**to add, remove and load schedule files for analysis.

- Logic+ supports importing most schedule file formats, including XER and MPP. You can add files or folders.
- You can also open schedule files from the same project that are in different formats.

---

### Select schedule for analysis

Use the schedule details displayed to decide which files to include in analysis.

➡️ Navigation: Bottom tab bar > List of Schedules

👉 Nominate Schedule Files: Choose which files to include in the traceback analysis and select a baseline schedule.

👉 Is Baseline? - Select the file to be used as the baseline schedule. You can only have one baseline file selected.

👉 Include in analysis? - Select the files that should be included in the analysis

![](https://lware.com/wp-content/uploads/2025/04/image-44-1024x205.png)

💡Whenever you change the baseline or schedule files to be included in analysis, you need to **Load schedule files** for analysis. Remember to click '**GO**' to reload the files into the Schedule Viewer.

---

### Load schedule files for analysis

Whenever you change the baseline or file to be included in analysis, the **Scheduler Viewer**will be cleared. The '**GO**' button needs to be clicked to reload the files and perform necessary calculations to support activities in Logic+.

➡️ Navigation: Bottom tab bar > List of Schedules

👉 Click '**GO**' to reload Gantt based on file selections

![](https://lware.com/wp-content/uploads/2025/04/image-14.png)

---

### Add schedule files or folders

Add new files or an entire folder to your Logic+ project.

➡️ Navigation: Bottom tab bar > List of Schedules > Add files

![](https://lware.com/wp-content/uploads/2025/04/image-8.png)

➡️ Navigation: Bottom tab bar > List of Schedules > Add folder

![](https://lware.com/wp-content/uploads/2025/04/image-12.png)

💡Schedule files can also be added used from the top menu File > Add Schedule.

---

### Remove schedule files

Remove schedule file from the project and the database.

➡️ Navigation: Bottom tab bar > List of Schedules > Delete schedule files

![](https://lware.com/wp-content/uploads/2025/04/image-9.png)

💡Schedule files can also be removed from the top menu File > Remove Schedule.

---